Schedule property
Jul 19th, 2011 at 9:07am
Print Post  
Hi Meppy,

              Could it be possible to have the schedule property as a dependency property?

Thanks.
  
Back to top
 
IP Logged
 
Meppy
God Member
*****
Offline


MindFusion support

Posts: 1783
Joined: Jul 20th, 2005
Re: Schedule property
Reply #1 - Jul 19th, 2011 at 9:27am
Print Post  
The Schedule property is already a dependency property in the latest release of the control. Please, download the latest version from our clients area here.

Regards,
Meppy
  
Back to top
 
IP Logged
 
zodraz
YaBB Newbies
*
Offline


I love YaBB 1G - SP1!

Posts: 29
Joined: Jan 14th, 2011
Re: Schedule property
Reply #2 - Jul 19th, 2011 at 9:53am
Print Post  
Hi,

      I have downloaded from clients are the PlannerLite 2.3.1. And when I try to attach a binding like:

<planner:Calendar x:Name="calendar"  Schedule="{Binding XXXX}">

Visula studio 2010 gives me this error:"Value cannot be null.Parameter name value"

Thanks
  
Back to top
 
IP Logged
 
Meppy
God Member
*****
Offline


MindFusion support

Posts: 1783
Joined: Jul 20th, 2005
Re: Schedule property
Reply #3 - Jul 19th, 2011 at 11:34am
Print Post  
Calendar.Schedule indeed raises an exception when you attempt to set it to null. I have sent you a private message with a link to a new build, which ignores null values.

Let me know if it helps.

Regards,
Meppy
  
Back to top
 
IP Logged
 
zodraz
YaBB Newbies
*
Offline


I love YaBB 1G - SP1!

Posts: 29
Joined: Jan 14th, 2011
Re: Schedule property
Reply #4 - Jul 19th, 2011 at 11:35am
Print Post  
Thanks Meppy.I am checking it now!
  